Basically the people on the project side came over very well. They said infill and compacting should be done by the end of next week. (an ideal post Derby update) The piling work will accelerate of course once that's done.
Work on the structure itself is well underway off site and will be delivered (I'd assume by ship) when needed and assembled like meccano.
During the Q & A questions where asked on finance, no update. Another question asked on finance timescale was glossed over.
Expect a piece in the Echo tonight.