Interesting bit:
Adding offsite into the mix makes change even more challenging. “I am always very clear with the client in the early stages: MMC can deliver quicker programmes but if you want an aspirational programme, you also have to understand you cannot also have continuous change,” says Jacques.
The client at Everton was on board with this approach, he says, but a new owner arrived part way through the project and changes to how the hospitality would work led to between £50m and £60m of changes, with the final cost being £610m.
“In overall terms that’s just under 10% of the project cost,” says Jacques.

Stadium building: what makes a winning project? - Construction Management
For contractors, a stadium project can be a triumph – or mean a major loss. Kristina Smith asked three experts what the ingredients of a successful stadium project should be.