New Everton Stadium


So, don't tell us the distance then. :lol:


Doesn't tell us the distance, but very usefully starts off with a map at this scale.

Screenshot 2025-05-15 at 14.34.07.webp
 
BMD was 90% complete about 8 months ago, so nice of somebody to give you that scoop 😀 Did they tell you what concrete they were referring to???? Vast majority of BMD concrete was pre fabricated off site, and brought to site. There is more chance of Katie Price retiring her fanny, than there is of Everton ever playing another prem game at Goodison after Sunday.

The whole of the corporate areas have been gutted out and required wiring etc. it's still just big empty rooms with plaster board at the moment.

Not saying it will be delayed but not sure how long it takes to do all those areas
 
Keeping GP provides a back up if the rumoured delays to BMD are true.
I’ve been told that BMD is 90% on track so hopefully they’ll get it done in time including safety certification etc.
Not ideal but apparently there are a number of LOR issues that will need resolving such as the concrete is cracking because they dried it too quick.
The recent pitch relay was not in the original plans - it was required because the foundations weren't deep enough to hold rugby posts.
This is the bit that exposed you for talking wham I'm afraid.

I know beyond a shadow of a doubt that this is incorrect. It was always the plan.
 

How mad is it that the club didn't get involved in a kind of All or Nothing series documenting behind the scenes at the last season of Goodison park? Joke really.
 